Date: The contract was signed in August 2012,
Completed in February 2017
Name of the contract: Beylagan city Receiving facilities
Construction and Water Supply Systems and Sewerage
Network Restoration
(Loan from the Asian Development Bank)
Contract value: $ 66,005,853.85
Customer: Azersu OJSC
Main works:
* Construction of 5 110m deep artesian wells,
Installation of submersible pumps Q = 63m3 / s, H = 110m,
N = 32kW, n = 3000 rpm;
* Construction of 2x500m3 and 2x2000m3 reservoirs,
Rehabilitation of 1x2000m3 reservoir;
* Construction of 2 Watchtower houses;
* Construction of 2 shutter chambers;
* Construction of 2 pumping stations (3 water pumps
installation Q = 200m3 / s, H = 70m, N75kW, n = 2970 rpm),
Renovation of 2 pumping stations (4 pumps Q = 110m3 / s,
H = 70m, N = 45kW, n = 2950 rpm);
* Construction of chlorination building;
* Construction of generator / transformer stations;
* Construction of water collector from PE D160-225mm pipes 1527m;
* Construction of 8590m main water line from PE D450mm pipes;
* Construction of 91631m long water line from PE D160-450mm pipes;
* 5846 water house combination;
* 88636m long sewer from PE D200-800mm pipes
network construction (D800mm-948m);
* 5250 units sewer house combination
* Construction of 2230 observation wells