CONTRACTS CONCLUDED WITH AGENCY ON RECONSTRUCTION AND REHABILITATION OF AREAS OF AZERBAIJAN REPUBLIC:
REPAIRING-REHABILITATION WORKS OF 1ST AND 2ND BUILDINGS OF AZERBAIJAN STATE OIL ACADEMY
INFORMATION:
The executed rehabilitation works were financed by state budget.
The works started on May of 2006 and completed on September of 2006 with execution of high quality and in accordance to the drawings.
Main executed works: rehabilitation of facad covers of buildings, painting, improvement of yard.
65 specialist and workers, 3 lorries, 1 crane were involved for construction works.
REHABILITATION OF AZERBAIJAN TECHNICAL UNIVERSITY
INFORMATION:
The executed rehabilitation works were financed by state budget.
The works started on December of 2007 and completed on January of 2008 with execution of high quality and in accordance to the drawings.
Main executed works: rehabilitation of facad covers of buildings and lighting.
43 specialist and workers, 2 lorries, 2 crane were involved for construction works.
BAKI ŞƏHƏRI, XƏTAI RAYONUNDA 1296 ŞAGIRDLIK 59 ORTA MƏKTƏBIN TIKINTISI
INFORMATION:
The executed rehabilitation and construction works are carried out by credit of Saudi Development Fund.
The works started on November of 2005 and completed on January of 2008 with execution of high quality and in accordance to the drawings.
Main executed works: construction works of 3 stored, 3 building of school from monolyth r/concrete and cubics, internal and external finishing works and insatllation of communication lines, rehabilitation of old building.
165 specialist and workers, 3 excavators, 2 tractors, 10 lorries, 2 crane and 10 concrete mixers were involved for construction works.
REHABILITATION OF 72 RESIDENTIAL HOUSES IN MIRZENAGILLI VILLAGE OF FUZULI RAYON
INFORMATION:
The executed rehabilitation works were financed by state budget.
The works started on September of 2009 and completed on December of 2009 with execution of high quality and in accordance to the drawings.
Main executed works: rehabilitation of houses from monolyth r/concrete, painting works, internal finishing works.
110 specialist and workers, 1 tractor, 8 lorries, 1 crane were involved for construction works.
REHABILITATION OF AZERBAIJAN STATE PAINTING ACADEMY
INFORMATION:
The executed rehabilitation works were financed by state budget.
The works started on August of 2009 and completed on September of 2010 with execution of high quality and in accordance to the drawings.
Main executed works: rehabilitation of roof of building, renovation of doors and windows, renovation of sanitary units, internal and external finishing works.
71 specialist and workers, 5 lorries, 1 crane were involved for construction works.
REHABILITATION WORKS OF INTERNAL WATER AND SEWER LINES OF 41 MULTISTOREY COMMUNAL RESIDENTIAL HOUSES IN ACCORDANCE WITH THE CONSTRUCTION OF NEW WATER AND SEWERAGE NETWORKS IN AGDASH TOWN.
INFORMATION:
The executed rehabilitation works were financed by state budget.
The works started on November of 2009 and completed on May of 2010 with execution of high quality and in accordance to the drawings.
Main executed works: rehabilitation of water and sewerage lines of buildings.
44 specialist and workers, 2 excavators, 1 tractor, 4 lorries, 1 crane were involved for construction works.
RECONSTRUCTION OF WATER SUPPLY AND SEWERAGE SYSTEMS FOR ZAGATALA AND OGUZ CITIES (1ST STAGE)
INFORMATION:
The executed construction works were financed by state budget.
The works started on October of 2010 and completed on May of 2014 with execution of high quality and in accordance to the drawings.
Value of contract: 8 083 000 manat .
Main executed works: construction of horisontal water intake area, water intake structures, laboratory buildings, chlorination plant, checkpoints for each town; construction of main transmission line from d=300mm polyethylene pipes (2310m) və d=350mm steel pipes (5980m); construction of water reservoirs 2x1000m3 and 1x1500m3
108 specialist and workers, 5 excavators, 2 tractors, 11 lorries, 2 crane and 10 concrete mixers were involved for construction works
RECONSTRUCTION-REHABILITATION WORKS OF 16 RESIDENTIAL HOUSE IN HORADIZ CITY, 1 RESIDENTIAL HOUSE IN MOLLAMEHERRREMLI VILLIGE AND 2 RESIDENTIAL HOUSE IN YUXARI KURDMAHMUDLU VILLIAGE OF FUZULI RAYON
INFORMATION:
The executed rehabilitation works were financed by state budget.
The works started on September of 2011 and completed on December of 2011 with execution of high quality and in accordance to the drawings.
Main executed works: rehabilitation of every damaged residential houses, plastering and painting works of internal and external walls, renovation of roofs, doors and windows are changed.
142 specialist and workers, 3 excavators, 1 tractors, 12 lorries, 2 crane and 2 concrete mixers were involved for construction works
CONSTRUCTION OF TREATMENT PLANTS FOR SUPPLYING THE SETTLEMENTS OF GENJE CITY, SAMUKH RAYON (NEBIAGALI SETTLEMENT) AND OTHER LIVING SETTLEMENTS WITH POTABLE WATER FROM WATER RESERVOIR CONSTRUCTED ON SHEMKIR RIVER (I STAGE)
INFORMATION:
The executed constuction works were financed by state budget.
The works started on September of 2011 and completed on March of 2012 with execution of high quality and in accordance to the drawings.
Main executed works: excavation of rocks by explosion, monolyth r/concrete works
53 specialist and workers, 5 excavators, 3 tractors, 5 lorries, 5 concrete mixers and machine and equipments for explosion works in rocks were involved for construction works
RECONSTRUCTION OF WATER SUPPLY AND SEWERAGE SYSTEMS FOR ZAGATALA AND OGUZ CITIES (2ND STAGE)
INFORMATION:
The executed construction works were financed by state budget.
The works started on October of 2011 and completed on June of 2014 with execution of high quality and in accordance to the drawings.
Value of contract: 69 384 000 manat.
Main executed works: construction of water reservoirs 1x1000m3 and 1x1500m3, construction of water line and networks by using of D20:D400mm pipes – 280 980m; construction of main transmission line by using of D280:D377mm pipes – 18 376m; construction of sewer line and networks by using of D160:D500mm pipes – 261 988m; construction of artesian wells, transformer substation, chlorination plant, water treatment structures.
190 specialist and workers, 6 excavators, 2 tractors, 14 lorries, 2 crane and 5 concrete mixers were involved for construction works
CONSTRUCTION OF WASTE WATER TREATMENT PLANT AND RELATED STRUCTURES FOR OGUZ AND ZAGATALA RAYONS (INSTALLATION OF EQUIPMENTS)
INFORMATION:
The executed construction works were financed by state budget.
The works started on December of 2012 and completed on June of 2014 with execution of high quality and in accordance to the drawings.
Value of contract: 14 498 912 manat .
Main executed works:
Purchasing, installation and launching of structure and equipments for treatment
30 specialist and workers, 5 lorries, 2 crane were involved for construction works
CONSTRUCTION OF WASTE WATER TREATMENT PLANT AND RELATED STRUCTURES FOR OGUZ AND ZAGATALA RAYONS (CONSTRUCTION WORKS-3RD STAGE)
INFORMATION:
The executed construction works were financed by state budget.
The works started on December of 2012 and completed on June of 2014 with execution of high quality and in accordance to the drawings.
Value of contract: 10 297 891 manat
Main executed works:
construction of pre teratment units, biological treatment units,chemical treatment units, outlet structures, sludge handling units, administrative buildings
75 specialist and workers, 3 excavators, 1 tractors, 7 lorries, 1 crane and 5 concrete mixers were involved for construction works