CONSTRUCTION OF ENGINEERING FACILITIES OF CONSTRUCTION AREA (INCLUDING CONSTRUCTION OF TEMPORARY ROADS AND PROTECTIVE DRAINAGE) AND 225 RESIDANTAL HOUSES IN NEW SETTLEMENT FOR 450 REFUGEES FAMILY IN ADMINISTRATIVE AREA OF SABUNCHU RAYON OF BAKU CITY.

INFORMATION:

The executed construction works were financed by state budget.

The works started on November  of 2006 and completed on May of 2007 with execution of high quality and in accordance to the drawings

Value of contract 26 678 732 manat.

Main executed  works: construction of 45 residential houses with 1 room, 111 residential houses with 2 rooms, 67 residential houses with 3 rooms and 2 residential houses with 4 rooms; excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines. Besides this construction of potable water line and networks, sewer line and networks, gaz line, electric line, drainage system were executed. construction of water reservoir with capacity of 500m3, improvement of area, asphalt covering of roads of area.

182 specialist and workers, 15  excavators, 5  tractors, 32  lorries, 3  crane, 10 concrete mixers were involved for construction works


CONSTRUCTION OF OLIMPIC SPORT COMPLEX IN GUZANLI SETTLEMENT OF AGDAM.

INFORMATION:

The executed construction works were financed by state budget.

The works started on June  of 2006 and completed on January of 2008 with execution of high quality and in accordance to the drawings

Value of contract 3 186 000 manat.

Main executed  works: construction of complex building with total construction area 4 022m2 from monolyth r/concrete and masonry works from cubics, internal and external finishing works, engineering communication lines.

84 specialist and workers, 5  excavators, 1  tractors, 13  lorries, 2  crane, 10 concrete mixers were involved for construction works


CONSTRUCTION OF 202 RESIDENTIAL HOUSES IN NEW SETTLEMENT OF FUZULI RAYON AREA

INFORMATION:

The executed construction works were financed by state budget.

The works started on June  of 2007 and completed on December of 2007 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 33 residential houses with 1 room, 93 residential houses with 2 rooms, 68 residential houses with 3 rooms and 8 residential houses with 4 rooms, excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

128 specialist and workers, 10  excavators, 4  tractors, 15  lorries, 2  crane, 10 concrete mixers were involved for construction works


CONSTRUCTION OF 100 RESIDENTIAL HOUSES IN NEW SETTLEMENT FOR 500 REFUGEE FAMILIES ON AREA OF BEYLAGAN RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on July  of 2008 and completed on October of 2008 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 9 residential houses with 1 room, 45 residential houses with 2 rooms, 44 residential houses with 3 rooms and 2 residential houses with 4 rooms, excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

122 specialist and workers, 9  excavators, 3 tractors, 12  lorries, 3  crane, 9 concrete mixers were involved for construction works


CONSTRUCTION OF OLIMPIC SPROT COMPLEX IN HORADIZ TOWN OF FUZULI RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on April  of 2009 and completed on May of 2010 with execution of high quality and in accordance to the drawings

Value of contract: 8 668 161 manat.

Main executed  works: construction of complex building with total construction area 4 200m2 from monolyth r/concrete and masonry works from cubics, internal and external finishing works, engineering communication lines.

90 specialist and workers, 5  excavators, 1 tractor, 12  lorries, 2  crane, 8 concrete mixers were involved for construction works


CONSTRUCTION OF  74 RESIDENTIAL HOUSES TOGETHER WITH SECONDARY SCHOOL WITH 15 CLASS ROOM IN NEW SETTLEMENT FOR REFUGEES OF 596 FAMILIES IN AREA OF GORANBOY RAYON.

INFORMATION:

The executed construction works were financed by state budget.

The works started on June  of 2009 and completed on October of 2009 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 43 residential houses with 3 rooms and 31 residential houses with 4 rooms, excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

97 specialist and workers, 7  excavators, 2 tractor, 10  lorries, 4 crane, 10 concrete mixers were involved for construction works


CONSTRUCTION OF  70 RESIDENTIAL HOUSES IN NEW SETTLEMENT FOR REFUGEES OF 689 FAMILIES IN AREA OF AGDAM RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on June  of 2010 and completed on October of 2010 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 10 residential houses with 1 room, 27 residential houses with 2 rooms, 24 residential houses with 3 rooms and 9 residential houses with 4 rooms, excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

95 specialist and workers, 7  excavators, 2 tractor, 10  lorries, 2 crane, 8 concrete mixers were involved for construction works


CONSTRUCTION OF A 5 STOREY RESIDENTIAL HOUSE NUMBER 1 WITH 60 APARTMENTS IN THE NEW BLOCK FOR 612 IDP FAMILIES IN THE TERRITORY YEVLAKH TOWN

INFORMATION:

The executed construction works were financed by state budget.

The works started on May of 2010 and completed on October of 2010 with execution of high quality and in accordance to the drawings

Main executed  works: total construction area 5 565m2, excavation of foundation, r/concrete framework works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engieering communication lines.

118 specialist and workers, 3 excavators, 2 tractor, 8  lorries, 2 crane, 10 concrete mixers were involved for construction works


CONSTRUCTION OF A 5 STOREY RESIDENTIAL HOUSE NUMBER 9 WITH 60 APARTMENTS IN THE NEW BLOCK FOR 556 IDP FAMILIES IN THE TERRITORY AGDJABEDI

INFORMATION:

The executed construction works were financed by state budget.

The works started on July of 2011 and completed on December of 2011 with execution of high quality and in accordance to the drawings

Main executed  works: total construction area 7 800m2, excavation of foundation, r/concrete framework works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engieering communication lines.

106 specialist and workers, 3 excavators, 2 tractor, 8  lorries, 2 crane, 10 concrete mixers were involved for construction works


CONSTRUCTION OF  52 RESIDENTIAL HOUSES IN NEW SETTLEMENT FOR REFUGEES OF 552 FAMILIES IN AREA OF AGDJABEDI RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on January  of 2011 and completed on May of 2011 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 37 residential houses with 2 rooms and 15 residential houses with 3 rooms, excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

92 specialist and workers, 5  excavators, 3 tractor, 10  lorries, 3 crane, 12 concrete mixers were involved for construction works


CONSTRUCTION OF  36 RESIDENTIAL HOUSES IN NEW SETTLEMENT FOR REFUGEES OF 195 FAMILIES IN AREA OF BERDE RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on April  of 2012 and completed on October of 2012 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 9 residential houses with 1 room, 7 residential houses with 2 rooms, 17 residential houses with 3 rooms and 3 residential houses with 4 rooms, excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

88 specialist and workers, 4  excavators, 2 tractor, 9  lorries, 2 crane, 11 concrete mixers were involved for construction works


CONSTRUCTION OF  46 RESIDENTIAL HOUSES IN NEW SETTLEMENT FOR REFUGEES OF 550 FAMILIES IN AREA OF  IMISHLI RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on April  of 2012 and completed on October of 2012 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 23 residential houses with 2 rooms and 23 residential houses with 3 rooms, excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

96 specialist and workers, 3 excavators, 2 tractor, 11  lorries, 2 crane, 10 concrete mixers were involved for construction works


CONSTRUCTION THE 42 RESIDENTIAL HOUSE AT THE NEW LIVING SETTLEMENT FOR 423 FAMILIES OF INTERNAL DISPLACED PERSONS ON SHEKI RAYON AREA

INFORMATION:

The executed construction works were financed by state budget.

The works started on March  of 2012 and completed on July of 2012 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 24 residential houses with 2 rooms and 18 residential houses with 3 rooms, excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

90 specialist and workers, 4 excavators, 2 tractor, 9  lorries, 2 crane, 10 concrete mixers were involved for construction works


CONSTRUCTION THE 5 STORE RESIDENTIAL HOUSE NUMBER 6 WITH 80 APARTAMENT FOR 1410 FAMILIES OF INTERNAL DISPLACED PERSONS ON MUSHFIGABAD SETTLEMENT OF GARADAGH RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on April of 2012 and completed on December of 2012 with execution of high quality and in accordance to the drawings

Main executed  works: total construction area 6 610m2, excavation of foundation, r/concrete framework works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engieering communication lines.

116 specialist and workers, 3 excavators, 2 tractor, 12 lorries, 2 crane, 12 concrete mixers were involved for construction works


CONSTRUCTION THE 9 STORED RESIDENTIAL HOUSES NO5 AT THE SETTLMENT FOR 502 FAMILIES OF INTERNAL DISPLACED PERSONS ON MINGECHEVIR CITY AREA

INFORMATION:

The executed construction works were financed by state budget.

The works started on December of 2011 and completed on December of 2012 with execution of high quality and in accordance to the drawings

Main executed  works: total construction area 5 400m2, excavation of foundation, r/concrete framework works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engieering communication lines.

130 specialist and workers, 3 excavators, 2 tractor, 12 lorries, 3 crane, 11 concrete mixers were involved for construction works


CONSTRUCTION THE 5 STORE RESIDENTIAL HOUSE NUMBER 7 WITH 60 APARTAMENT FOR 866 FAMILIES OF INTERNAL DISPLACED PERSONS ON HESENGAYA MUNICIPALITET AREA OF BERDE RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on March of 2013 and completed on November of 2013 with execution of high quality and in accordance to the drawings

Main executed  works: total construction area 6 140m2, excavation of foundation, r/concrete framework works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engieering communication lines.

112 specialist and workers, 3 excavators, 2 tractor, 10 lorries, 3 crane, 10 concrete mixers were involved for construction works


CONSTRUCTION THE 5 STORE RESIDENTIAL HOUSE NUMBER 18 WITH 60 APARTAMENT FOR 1500 FAMILIES OF INTERNAL DISPLACED PERSONS TEMPORARY LIVING IN HOSTELS IN  GENDJE CITY

INFORMATION:

The executed construction works were financed by state budget.

The works started on April of 2013 and completed on October of 2013 with execution of high quality and in accordance to the drawings

Main executed  works: total construction area 5 600m2, excavation of foundation, r/concrete framework works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engieering communication lines.

117 specialist and workers, 3 excavators, 2 tractor, 10 lorries, 2 crane, 10 concrete mixers were involved for construction works


CONSTRUCTION OF 63 RESIDENTIAL HOUSES FOR FAMILIES OF INTERNAL DISPLACED PERSONS ON NEW SETTLEMENT FOR 632 FAMILIES WITH NECCESSARY INFRASTRUCTURES IN AGDAM RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on February of 2014 and completed on July of 2014 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 12 residential houses with 2 rooms, 25 residential houses with 3 rooms and 21 residential houses with 4 rooms; excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

120 specialist and workers, 5 excavators, 3 tractors, 12  lorries, 2 crane, 10 concrete mixers were involved for construction works


CONSTRUCTION OF 53 RESIDENTIAL HOUSES FOR FAMILIES OF INTERNAL DISPLACED PERSONS ON NEW SETTLEMENT FOR 320 FAMILIES WITH NECCESSARY INFRASTRUCTURES IN BEYLAGAN RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on March of 2014 and completed on July of 2014 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 7 residential houses with 1 rooms, 30 residential houses with 2 rooms, 12 residential houses with 3 rooms and 4 residential houses with 4 rooms; excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

94 specialist and workers, 5 excavators, 2 tractors, 10  lorries, 2 crane, 12 concrete mixers were involved for construction works


CONSTRUCTION OF 65 RESIDENTIAL HOUSES FOR FAMILIES OF INTERNAL DISPLACED PERSONS ON NEW SETTLEMENT FOR 600 FAMILIES WITH NECCESSARY INFRASTRUCTURES IN  GOYGOL RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on March of 2014 and completed on July of 2014 with execution of high quality and in accordance to the drawings

Main executed  works: construction of 1 residential house with 1 room, 14 residential houses with 2 rooms, 32 residential houses with 3 rooms and 2 residential houses with 4 rooms; excavation of foundations, r/concrete works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engineering communication lines.

108 specialist and workers, 3 excavators, 2 tractors, 10  lorries, 2 crane, 12 concrete mixers were involved for construction works


CONSTRUCTION THE 7 STORE RESIDENTIAL HOUSE NUMBER 5 WITH 42 APARTAMENT FOR 588 FAMILIES OF INTERNAL DISPLACED PERSONS WITH ALL NECESSARY SOCIAL-TECHNIC INFRASTRUCTURES  IN BARDA RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on June of 2014 and are continuing

Main executed  works: total construction area 5 000m2, excavation of foundation, r/concrete framework works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engieering communication lines.

130 specialist and workers, 3 excavators, 2 tractor, 10 lorries, 3 crane, 12 concrete mixers are involved for construction works


CONSTRUCTION THE 9 STORE RESIDENTIAL HOUSE NUMBER 2 WITH 54 APARTAMENT FOR 594 FAMILIES OF INTERNAL DISPLACED PERSONS WITH ALL NECESSARY SOCIAL-TECHNIC INFRASTRUCTURES  IN MINGECHEVIR RAYON

INFORMATION:

The executed construction works were financed by state budget.

The works started on June of 2014 and are continuing

Main executed  works: total construction area 6 140m2, excavation of foundation, r/concrete framework works, masonry of walls and partitions, installation of doors and windows, construction of floor and ceilings, roofing, internal and external finishing works, engieering communication lines.

132 specialist and workers, 3 excavators, 1 tractor, 12 lorries, 2 crane, 13concrete mixers are involved for construction works